EXECUTIVE SUMMARY

 i.    This Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. SPW 07/2020 “Environmental Team for Construction of Yuen Long Effluent Polishing Plant Stage 1”. Drainage Services Department (DSD) has appointed Fugro Technical Services Limited (FTS) to undertake the Environmental Team services for the project and implement the EM&A works.

ii.    This is the 9th Monthly EM&A Report for the Contract which summaries findings of the EM&A programme during the reporting period from 1 December 2021 to 31 December 2021. As informed by the Contractor, major activities in the reporting month were:

 

Breaches of Environmental Quality Performance Limits (AL levels)

 

iii.     No Action and Limit Level exceedance was recorded for air quality monitoring and construction noise monitoring in the reporting month.

iv.    No Action and Limit Level exceedance was recorded for water quality monitoring in the reporting month.  

v.    No Action / Limit exceedance was recorded for noise levels at stations (NMS1 and NMS2) in close proximity to the two active ardeid night roosts (ANR1 and ANR2) observed within the Survey Area during the reporting month.

vi.    No Action / Limit exceedance for the ecological monitoring of birds in the reporting month.

vii.     No corrective actions were required according to the Event-Action Plans.


 

Land Contamination

 

viii.    Regular site inspection was carried out to ensure the recommended mitigation measures are properly implemented. Site investigation (SI) work was completed by 4th August 2021 and the signed final Contamination Assessment Report (CAR) for Main Storeroom & Workshops was submitted to EPD on 1 November 2021. The signed final Contamination Assessment Report (CAR) for Mechanical Workshop was submitted to EPD on 23rd November 2021. No contaminated soil and ground water was found within the Main Storeroom & Workshop and the Mechanical Workshop, hence no remedial action is required.

Complaint Log

ix.    No complaints were received in the reporting period.

Notifications of any Summons and Successful Prosecutions

x.    No notifications of summons and prosecutions were received in the reporting period.

Reporting Change

xi.    There were no reporting changes during the reporting month.

Future Key Issues

xii.    The main works will be anticipated in the next three months are as follow:

 

 


 

Contents

1.        INTRODUCTION  

2.       AIR QUALITY 

3.       NOISE 

4.       WATER QUALITY 

5.       ECOLOGY MONITORING  

6.       LANDSCAPE AND VISUAL 

7.       LAND CONTAMINATION  

8.       SITE INSPECTION AND AUDIT 

9.       NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONS 

10.      IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURE 

11.      FUTURE KEY ISSUES 

12.      CONCLUSION AND RECOMMENDATION  

 


 


Tables

Table 1.1  Contact Information of Key Personnel

Table 1.2 Environmental Licenses, Notification and Permits Summary

Table 2.1 Air Quality Monitoring Equipment

Table 2.2 Air Quality Monitoring Location

Table 2.3 Summary of Air Quality Monitoring Results       

Table 2.4 Comparison of 1-hr TSP data with EIA predictions

Table 3.1 Construction Noise Monitoring Equipment

Table 3.2 Monitoring Parameters and Frequencies of Noise Monitoring

Table 3.3 Construction Noise Monitoring Location

Table 3.4 Summary of Construction Noise Monitoring Results

Table 3.5 Comparison of Noise monitoring data with EIA predictions

Table 4.1  Water Quality Monitoring and Sampling Equipment

Table 4.2 Monitoring Parameters and Frequency

Table 4.3 Coordinates of Water Quality Monitoring Locations

Table 4.4 Summary of Water Quality Exceedance

Table 5.1 Noise Monitoring Parameters (For Active Ardeid Night Roost Survey)

Table 5.2 Active Ardeid Night Roost Survey Findings

Table 5.3 Noise Monitoring Results (For Active Ardeid Night Roost Survey)

Table 5.4 Noise Monitoring Parameters

Table 5.5 Abundance of all Avifauna Species

Table 5.6 Abundance of Species of Conservation Importance

Table 5.7 Shannon Diversity Index Value of all Avifauna Species

Table 5.8 Shannon Diversity Index Value of Species with Conservation Importance

Table 5.9 Wetland habitat utilization of all avifauna species

Table 5.10 Wetland habitat utilization of avifauna species of conservation importance

Table 5.11 Wetland habitat utilization of overwintering avifauna species

Table 5.12 Noise Monitoring Results (For Ecological Monitoring of Birds)

Table 8.1 – Waste Generated by the Construction and Disposal Ground

Table 10.1 – Summary of EP Submissions Status


 


Figures

Figure 1         Location of Proposed Yuen Long Effluent Polishing Plant

Figure 2         Air Quality Monitoring Locations

Figure 3         Noise Monitoring Locations

Figure 4         Water Quality Monitoring Locations

Figure 5         Ecology Monitoring Locations


Appendices

Appendix A    Construction Programme

Appendix B    Project Organization Chart

Appendix C    Action and Limit Levels

Appendix D   Calibration Certificate of Monitoring Equipment

Appendix E    Environmental Monitoring Schedule

Appendix F    Monitoring Results

Appendix G   Wind Data

Appendix H   Event and Action Plan

Appendix I     Waste Flow Table

Appendix J    Implementation Status of Environment Mitigation Measures

Appendix K    Weather and Meteorological Conditions

Appendix L    Cumulative statistics on Environmental Complaints, Notifications of Summons and Successful Prosecutions

Appendix M   Summary of the ET Leader’s Site Environmental Audit in the Reporting Month

Appendix N   Outstanding Issues and Deficiencies

Appendix O   Active Night Roost Monitoring Area and Vantage Points; and Noise Monitoring Stations

Appendix P    Ecological Bird Monitoring Area with Locations of Point Count Sites and Transect Route